ITarian Help

Find the desired product help

ITarian

ITarian

Service Desk Admin Guide

English

Print Help Download Help
Service Desk Staff Panel > Manage Projects
  • Introduction To Service Desk Module
    • Quick Start
    • Login To The Service Desk Module
  • Service Desk Admin Panel
    • Admin Panel Dashboard
      • View The Dashboard And Export Reports
      • View Alerts & Notifications
    • Service Desk Configuration
      • Company Profile And Support Portal Settings
      • Service Desk System Settings
      • Ticket Settings And Options
      • User Registration Settings
      • Email Settings And Options
      • Access Control Settings
      • Knowledge Base Settings And Options
      • Autoresponder Settings
      • Configure Alerts And Notices
      • Configure Two Factor Authentication
    • Manage Service Desk Components
      • Ticket Categories
      • Ticket Filters
      • Service Level Agreements (SLA)
      • API Keys
      • Client Portal Pages
        • Configure Your Support Center Page
      • Forms
      • Custom Lists
      • View And Manage Asset Types
      • Manage Materials And Expense Items
      • Manage Charging Plans
    • Email Management
      • Setup Your Support Email Addresses
      • Block User Email Addresses
      • Email Templates
      • Test Outgoing Email Settings
    • Manage Time Sheets
    • Manage Staff
      • Staff Members
      • Staff Roles
      • Departments
      • Time Sheet Templates
      • Material Approval
    • Manage Announcements
    • Generate Reports
      • Time Log Reports
      • Ticket Report
      • Asset Reports
      • Service Types Reports
      • Department Ticket Reports
      • Agent Reports
      • Users Reports
      • Resource Appointment Reports
      • Scheduled Reports
    • Finance
      • Generate Cost Reports
      • Manage Contracts
  • Service Desk Staff Panel
    • Staff Panel Dashboard
      • View The Dashboard And Export Reports
      • View Staff Members
      • My Profile
    • Manage Users And Customers
      • Manage Users
      • Manage Customers
    • Manage Tickets
      • Ticket Details
    • Manage Knowledgebase
      • FAQs
      • Manage FAQ Categories
      • Canned Responses
    • Manage Projects
    • Manage Staff Time Sheets
    • Manage Calendars
  • Appendix 1 - Field Types In Custom Forms And Custom Lists
  • Appendix 2 - Ticket Priorities
  • Appendix 3 - How Charging Works In Service Desk
  • About ITarian

Manage Projects

 

Click 'Staff Panel' > 'Projects'

  • Service desk projects allow staff to plan delivery time-lines for larger scale tasks which may involve multiple sub-tasks.
  • Each task can be assigned a total duration, completion percentage and billable time.
  • You can also create sub-tasks and associate a task with one or more tickets.
  • Projects are displayed as a Gantt chart, allowing you to easily track overall progress.




Column Headers
  • Project Name - The project label.
  • Duration -  The total duration of a project is the combined duration of its individual tasks.
    • Completion – The overall completion rate is calculated from the completion percentage of the project’s individual tasks.
      • Time Spent – Total time spent in individual tasks, sub tasks and tickets.
      • Billable Time - Total billable time spent in individual tasks, sub tasks and tickets.
      • Start Date – Date at which the project was started, or is due to start.
      • End Date – Date and which the project was completed, or is due to be completed. Completion date is calculated from the total duration of individual tasks in the project.
      From the Projects interface, staff members can:
      • Create a new project and add Tasks and Sub Tasks
      • View the project status and update it
      • Remove a project

      Create a new Project


      Staff members can create new projects and integrate tasks to it. You should specify a duration for each task/sub-task.


      Create a new project

      • Click 'Add New Project' from the 'Projects' interface




      The Project Properties dialog will appear.

      • Enter a name for the project
      • Enter the project start date by clicking the calendar icon beside 'Start Date'
      • Click 'Save'

      A new project will be created and the project page will be displayed. The project title will be added as the root task to the project. You can add sub-tasks at required hierarchy levels and associate tickets with them.




      • To add a sub-task:
      • Select the root task and click 'Add New Task' button at the top right




      The 'Add/Edit Task' dialog will appear.

      • Enter the name of the task
      • Predecessor (optional). Select a task which must be completed before the new task can begin
      • Enter the time required (in hours) to complete the task in the 'Duration' field
        • If the task is in-progress, enter the completion percentage in the 'Completion %' 'field

        The time spent field will be automatically populated from the entered values.




        • Enter the quantity of chargeable hours in the 'Billable Time' field using the sliders and click 'Save'.
        • Repeat the process to add more tasks.
        • To add another main task, select the project and click 'Add New Task'. This will create a sibling task.



        The 'Add/Edit Task' dialog will appear.

        • Enter the name for the task.
        • Enter the predecessor to continue from the previous task/subtask.
        • Enter the time duration required (in hours) to complete the task in the 'Duration' field
        • If the task is in-progress, enter the completion percentage on it in the 'Completion %' 'field

        The time spent field will be automatically populated from the entered values.

        • Enter the quantity of chargeable hours in the 'Billable Time' field using the sliders and click 'Save'.
        • Repeat the process to add more tasks.
        • To add a sub-task to a main-task: 
        • Select the parent level task
        • Click the 'Add New Task' button and repeat the process as outlined above.

        The duration and completion percentage of the parent task will be updated as per the figures entered in the corresponding fields of all sub-tasks.

        • To link a ticket to a task
        • Select the task/sub-task to which the ticket is to be linked and click 'Add New Ticket' button




        The Add/Edit ticket dialog will appear.  

        • Enter the ticket number or subject of the ticket in the 'Search Ticket' field and choose the ticket to be added from the drop-down options. Please note that the time spent will be displays the actual time spent based on the duration hrs and completion percentage entered.
        • Enter the predecessor to continue from the previous task/subtask.
        The time spent and billable time will be automatically populated for the progress of the ticket so far. 
        • Enter the duration for the ticket completion and the completion percentage in the respective fields. 




        • Click 'Save'.

        The ticket will be linked to the task.




        The time spent on the task and the billable time will be fetched from the ticket details and automatically updated. You can also add sub-tickets to a task/sub-task, which is processed concurrently with the main tickets. The duration and completion percentage of the sub tickets will not count towards the total duration and completion percentage of the project. 

        • To delete a task, sub-task, ticket or a sub-ticket, select the item and click 'Delete Item'.
        • Click 'Save' in the project viewer interface to save your changes.

        View the Project Status and Update it


        Administrators or staff members can view the status of individual tasks and sub-tasks, tickets and sub-tickets and overall progress of a project from the Project Viewer interface.


        View a project

        • Open the Projects interface by clicking 'Projects' on the left from the 'Staff Panel'
        • Click a project name to open the project time-line:




        The tasks, sub-tasks, tickets and sub-tickets added to the project are displayed as a tree structure in the first column. The left hand side pane shows the details of each item and the right hand side pane shows progress of each item as a Gannt chart.


        Project Viewer - Column Descriptions

        Column Header

        Parent level Task

        Child Task

        Tickets/Sub Tickets

        Duration

        The total duration of a parent level task is the combined duration of its child tasks and tickets.

        Duration of the individual task, as entered while adding/editing it or the combined duration of the tickets linked to it.

        Note: Sub tickets are excluded for calculation of duration.

        Duration of the ticket

        Completion

        The total completion status of a parent level task is calculated from the completion percentages of child tasks and tickets.

        The completion percentage of individual task or the combined completion percentages of tickets linked to it.

        Note: Sub tickets are excluded for calculation of completion status.

        Completion percentage of individual ticket

        Time Spent

        Total time spent in child tasks and tickets.

        Time spent on individual task or the combined time spent on tickets linked to it, excluding the sub-tickets.

        Note: Sub tickets are excluded for calculation of time spent.

        Time spent on individual ticket

        Billable Time

        Total billable time spent in child tasks and tickets.

        Billable time spent on individual task or the combined billable time spent, from tickets linked to it, excluding the sub-tickets.

        Note: Sub tickets are excluded for calculation of billable time spent.

        Billable time spent on individual ticket

        Start

        Date at which the task was started, or is due to start.

        Date at which the task was started, or is due to start.

        Date at which the ticket was started.

        End

        Date and which the task was completed, or is due to be completed. Completion date is calculated from the total duration of child tasks.

        Date at which the individual task was completed, or is due to be completed. Completion date is calculated from the duration of the individual task or the total duration of tickets linked to it.

        Date at which the individual ticket was completed, or is due to be completed.


        • To add a new item, click the respective button from the top right and enter the details of the item in the 'Add/Edit Task' or 'Add/Edit Ticket' dialog. For more details, see the explanation above.

        Edit/update a task

        • Click the pencil icon at the left of the item or double click on the respective bar in the Gannt chart.
        The Add/Edit Task dialog will appear for the respective task.

        Parent Level Task



        • Task Name - Displays the name of the task. You can change the name of the task by directly editing the field.
        The 'Time Spent', 'Duration Hrs', 'Completion % ' and 'Billable Time' are automatically populated from the sums of the respective values in the child tasks.
        • Click 'Save' for your changes to take effect

        Child Level or Terminal Task



        • Task Name - Displays the name of the task. You can change the name of the task by directly editing the field.
        • Predecessor - Displays the previous task/sub-task from which the present task has to be continued.
        • Time Spent - Displays the actual time spent based on the duration hrs and completion percentage entered.
        • Duration - Allows you to update the time duration required (in hours) to complete the task
        • Completion % - Allows you to update the completion percentage
        The time spent field will be automatically populated from the entered values.
        • Billable Time - Allows you update the billable time spent on the task
        • Click 'Save' for your changes to take effect
        The duration and completion percentage will automatically be updated for the parent task to which the child task is linked.
        • Click 'Save' in the 'Projects' interface

        Update a ticket or a sub-ticket

        • Click the pencil icon at the left of the item or double click on the respective bar in the Gannt chart.

        The 'Add/Edit Ticket' dialog will appear for the respective task.

        • To change the ticket item linked to the task, enter the new ticket number/subject of the ticket in the Search Ticket field.
        • To change the Duration, directly enter the new duration in the Duration field
        • To change the completion percentage, enter the new completion level in the Completion % field

        The 'Time Spent' and 'Billable Time' are fetched from the ticket and are uneditable.

        • Click 'Save' for your changes to take effect.

        The duration and completion percentage will automatically be updated for the task to which the ticket is linked.

        • Click 'Save' in the 'Projects' interface


        Remove a Project


        Projects that are completed or no longer required, can be removed from Service Desk.


        Remove project(s)

        • Open 'Projects' interface by clicking the 'Projects' tab from the 'Staff Panel'
        • Select the project(s) to be removed and click 'Delete'




        A confirmation dialog will appear.




        • Click 'Yes, Do it!' to remove the project

        Comodo Help
        • IT Platform:
        • Help
        • Scripts
        • Wiki
        • Forum
        • Developer
        • RMM
        • Patch Management
        • Service Desk
        • ITSM
        • Managed Service Provider
        • Managed Detection and Response
        • Ticketing System
        • Helpdesk
        • ITIL

        Copyright 2025 Itarian